Order status
The order can have the following states in the PPS:
-
Unscheduled
The order has no tickets. -
Scheduled
The order has at least one ticket with the Scheduled status. -
Released
The order has at least one ticket with the released status. -
In progress
The order has at least one ticket with the status In progress, In activity, Completed on the machine or Done and not all of the pieces were produced. -
Completed
All tickets of the order have the Completed status and the number of the pieces produced of all tickets is larger or the same as the produced pieces of the order.
As soon as an order is Completed, its data is automatically reported back to all possible source systems (ERP, ODBC). If not all of the planned pieces are produces, the order remains in the In progress status. The dispatcher can either complete the order manually or reknit the missing units in the framework of the current order, generating one or more additional tickets.