Output parameters
-
Operating times:
Working times in the knitwear factory -
Stop motions that occured during running production
-
earliest possible start of production of an order
(e.g. due to material delivery)
An earliest possible production start in the future can lead to allocations of a machine in the future, which must be observed when forecasting further orders.
Such orders that are scheduled via the earliest possible production start can force the STOLL PPS to divide the orders. -
latest possible production end of an order (deadline)
-
assumed production duration of an order
-
Information for orders that are already waiting for their production on the machine
-
Setup time or assumed production efficiency
The production efficiency is a percentage-based addition to the assumed production duration. This addition takes into account the typical delays in the production or the interim setup time of the machine.
In case of a large piece number, the setup time is a result of the production efficiency.
Additionally, there is the option of manually taking into account the knitting-in times by the dispatcher, adding times here