Times for the calculation
-
One or more orders are scheduled
Previously no production start can be established. -
The user changes the order
of the orders waiting on the machine or already scheduled - Machine reports back that the production of an order was started.
- Machine reports back that another piece of the order was produced.
=> Number of the produced pieces of an order + production duration up to now - Machine reports back that the production of an order was completed.
- Machine reports back that an order was taken out of the production / cancelled
In each case all the tickets on the machine and the related orders are updated.