Start Production
Start production:
- You are signed in as Senior Operator
.
- 1
- In the main navigation bar select the main area
Set up Order. - 2
- Tap on
Edit order in the bottom navigation bar.
- The window is displayed.

2 | Button for starting the production with the line number specified under (3).
|
3 | Display of the Sintral line number, at which the knitting program will be started. |
- 3
- If necessary, specify the desired line number for the production start under (3).
- 4
- Press the
Start production button:
- Production will get started without executing TP (Test Program)
Execute Test Program (TP) on the machine:
- You are signed in as Senior Operator
. - A knitting program is loaded.
İş emrini ayarla is enabled.
- 1
- Tap on
Deseni
düzenle in the bottom navigation bar. - 2
- Open the
Test tab. - 3
- Tap the
key. - The knitting ability of the knitting program will be checked.
- 4
- If TP ok, you can directly start the production by the
Üretimi başlat button.
: No TP is carried out automatically.